Chief Minister Capt Amarinder Singh laid the foundation stone of the ambitious 206-MW Shahpur Kandi dam project to be built on the Ravi

The project, when completed in 2022, will allow the country to control its share of the Ravi waters flowing into Pakistan

The CM was accompanied by Power Minister Gurpreet Singh Kangar and Gurdaspur MP Sunil Jakhar

This is the second such ceremony. On April 20, 1995, the then Prime Minister, PV Narasimha Rao, had laid the foundation stone and had claimed that the project will be completed in three years. However, the venture hit a roadblock due to various reasons

The dam has the potential to provide irrigation water to vast tracts of land in Punjab and J&K. The Indus Waters Treaty, which was signed between India and Pakistan in 1960, had envisaged that the country got full rights for the utilisation of waters of the Ravi, Beas and Sutlej. However, at present, some water of the Ravi flowed into Pakistan through Madhopur headworks and the dam plans to minimise it

The overall cost of the project is pegged at Rs 2,715.70 crore and is slated to be completed by June 2022,” an official said

The construction of the dam was initially approved by the Planning Commission in November 2001 but the work could not make much progress due to the fund crunch in the Punjab Government. Later when the work began, it again got halted following a dispute between Punjab and J&K. A series of meetings held bilaterally and the Centre finally paved the way for an agreement between the two states,” Jakhar said

The dam’s construction is expected to generate hundreds of jobs for both skilled and unskilled workers

An official disclosed that the dam had been designated as a ‘national project’ following which its construction would be monitored regularly by the Ministry of Water Resources. The Centre would extend whatever assistance is required by Punjab and J&K for the implementation of the project

Work halted repeatedly

April 20, 1995: The then Prime Minister, PV Narasimha Rao, laid the stone of the project and claimed it would be completed in three years. However, the venture hit a roadblock due to various reasons

November 2001: The dam work was initially approved by the Planning Commission but the work could not make much progress as the state was facing fund crunch Later when the construction work began, it again got halted following a dispute between Punjab and J&K

| Updated on: 14 - Mar - 2019
Search Tenders By Product: Dam Work Project
To view this paid Project you can either "Buy this Project" or subscribe our annual Project Alert Service and get access to all similar Projects. If you are registered member, please fill in the subscription form below . If not, please Register first.
Step 1 - Select a plan
Select Plan Unit Rate Subscription Validity
Rs. 29500 /-
Step 2 - If registered user, please fill below form
(*) Mandatory fields
Email Id *
States Interested In
Projects Interested In
Select Payment Type
Verification Code *
Note : As Goods and Services Tax is set to be implemented from 1st July 2017. The transition provisions under GST law applies to all services provided by e-Procurement Technologies Limited to its clients on or after 1st July 2017 and GST tax rate and other taxes are applicable as extra for all services provided.